Submittal Review Cycle

The three-folder workflow for submitting, reviewing, and revising shop drawings.

Overview

Completed shop drawings follow a three-folder workflow under 03_OUTGOING_Submittals/[PROJ.JOB_ScopeDescription]/:

03_OUTGOING_Submittals/
  PROJ.JOB_ScopeDescription/
    00_Internal_Review/    ← Engineer places drawings here for QA
    01_Outgoing/           ← Clean PDFs sent to client
    02_Returned/           ← Architect markups returned for FE review

Step-by-Step

1. Internal Review

  • Place completed shop drawings in 00_Internal_Review/.
  • Submit a PA Approval request via the Teams Approvals app, attaching a Box link to the internal review PDF.
  • The PM reviews first, then the PA. Both add Bluebeam comments to the PDF.

2. Revise if Denied

If denied at either stage:

  1. Pick up all Bluebeam comments from both PM and PA.
  2. Revise the drawings.
  3. Submit a new approval request (do not reuse the denied request).

3. Outgoing

After approval:

  • The PM exports a clean (comment-free) PDF copy to 01_Outgoing/.
  • The PM submits the drawing package to the client/architect.

4. Returned

When the architect returns marked-up drawings:

  • The PM places them in 02_Returned/.
  • The FE reviews all redlines and incorporates changes.
  • If changes are required, the cycle repeats (revised drawings go back to 00_Internal_Review/).

Submittal Status Tracking

Track submittal progress in the Epicor Production Report. Update the “Submittal” status field as the submittal progresses:

  • Internal Review
  • Submitted
  • Approved / Resubmitted

Key Principles

  • Never skip internal review. All drawings go through PA approval before client submission.
  • Keep folders clean. Only the current version of a drawing should be in each folder.
  • Pick up all comments. Both PM and PA comments must be addressed — not just the PA’s.
  • Track status in Epicor. The Production Report is the system of record for submittal progress.