Submittal Review Cycle
The three-folder workflow for submitting, reviewing, and revising shop drawings.
Related Documents: Approvals Process PE Release Preparation Folder Structure
Overview
Completed shop drawings follow a three-folder workflow under 03_OUTGOING_Submittals/[PROJ.JOB_ScopeDescription]/:
03_OUTGOING_Submittals/
PROJ.JOB_ScopeDescription/
00_Internal_Review/ ← Engineer places drawings here for QA
01_Outgoing/ ← Clean PDFs sent to client
02_Returned/ ← Architect markups returned for FE review
Step-by-Step
1. Internal Review
- Place completed shop drawings in
00_Internal_Review/. - Submit a PA Approval request via the Teams Approvals app, attaching a Box link to the internal review PDF.
- The PM reviews first, then the PA. Both add Bluebeam comments to the PDF.
2. Revise if Denied
If denied at either stage:
- Pick up all Bluebeam comments from both PM and PA.
- Revise the drawings.
- Submit a new approval request (do not reuse the denied request).
3. Outgoing
After approval:
- The PM exports a clean (comment-free) PDF copy to
01_Outgoing/. - The PM submits the drawing package to the client/architect.
4. Returned
When the architect returns marked-up drawings:
- The PM places them in
02_Returned/. - The FE reviews all redlines and incorporates changes.
- If changes are required, the cycle repeats (revised drawings go back to
00_Internal_Review/).
Submittal Status Tracking
Track submittal progress in the Epicor Production Report. Update the “Submittal” status field as the submittal progresses:
- Internal Review
- Submitted
- Approved / Resubmitted
Key Principles
- Never skip internal review. All drawings go through PA approval before client submission.
- Keep folders clean. Only the current version of a drawing should be in each folder.
- Pick up all comments. Both PM and PA comments must be addressed — not just the PA’s.
- Track status in Epicor. The Production Report is the system of record for submittal progress.