Folder Structure & File Management Outline

Project Organization Overview

The CWK Engineering folder structure organizes all project-related files. Consistent folder structure ensures efficient file location and collaboration across the engineering team.

Full Box Hierarchy

Box/
  Awarded/
    [4-digit ProjectCode]_[ProjectDescription]/
      01 Precon/
      02 Project Management/
        05_Material_Finish_Log/
      03 Engineering/
        01_INCOMING_Documents/
          00_Contract_Drawings_from_Precon/
          01_Addendum_Drawings_Post_Contract/
          02_Working_Set/
          03_Spec_Sheets/
          04_Coordination_Documents/
            _AdjacentSub_Drawings_Models/
            _Processed_Laser_Scans/
        02_WORKING_Drawings_Models/
          00_Lead_Project_Eng/
            _Shared_Display_Modes/
            _Shared_GH/
          01_FE_Models/
            [PROJ.JOB_ScopeDescription]/
            00_GS_Master_Models/
          02_CoverSheet_CommonPages/
          03_PE_Releases/
            [PROJ.JOB_ScopeDescription]/
              Production_Files/
              Production_Drawings/
            00_MT_WC_IP_MfgParts/
              [PROJ.M.000 or PROJ.W.000]/
        03_OUTGOING_Submittals/
          [PROJ.JOB_ScopeDescription]/
            00_Internal_Review/
            01_Outgoing/
            02_Returned/
      04 Purchasing/
      05 Shipping/

Always use Windows Explorer paths (not Box links) when referencing file locations in release forms and team communications.

PROJECT ROOT FOLDER

  • Location: Box/Awarded/
  • Contains all active projects

SPECIFIC PROJECT FOLDER

Naming Convention:

[4-digit ProjectCode]_[ProjectDescription]

Example: 1085_Lucas Retail Expansion and Security Pavilion

DEPARTMENTS Folder

Contains folders for all company departments:

  • 01 Sales (Precon)
  • 02 Project Management
  • 03 Engineering
  • 04 Purchasing
  • 05 Shipping

03 ENGINEERING Folder Structure

01_INCOMING_Documents

Contains all job-related documents received to date:

00_Contract_Drawings_from_Precon

  • Architectural drawing set from the client used for contract/bidding.
  • Copies become the working set.

01_Addendum_Drawings_Post_Contract

  • Updated architect drawings reflecting changes to existing jobs.

02_Working_Set

  • Organized contract drawings used by engineers for modeling and drafting.

03_Spec_Sheets

  • Detailed drawings (cut sheets) of devices/components for accurate modeling and submittals.

04_Coordination_Documents

  • Documentation for installation coordination:
    • _AdjacentSub_Drawings_Models/: Floor plans, 3D models from adjacent trades.
    • _Processed_Laser_Scans/: Cleaned 3D laser scan files.

02_WORKING_Drawings_Models

Houses working drawings and models:

00_Lead_Project_Eng

  • _Shared_Display_Modes/: Project-specific display modes for consistent submittal appearance.
  • _Shared_GH/: Shared Grasshopper scripts.

01_FE_Models

  • Individual job folders copied from _PROJ.JOB_ScopeDescription template and renamed to your job.
  • FE working file naming: [PROJ.JOB]_FE_[Description].3dm — e.g., 1094.002_FE_CashWrap.3dm
  • PE release file naming: [PROJ.JOB]_PE_YYYYMMDD.3dm — e.g., 1105.007_PE_20250124.3dm
  • 00_GS_Master_Models/: Grouped submittals master models.

02_CoverSheet_CommonPages

Project-level documents that attach to any full project submittal or record set:

  • Cover Sheet: Full project job index
  • General Requirements: Finish/material tags generated via the Engineering Toolkit from the TRA log
  • Master Floorplan / Keyplan: Per level, showing all awarded scope
  • Partition Plans: Field dimensions, ceiling heights, blocking, electrical, load calcs if needed
  • Pre-Submittal Sets: Scope/design intent clarification
  • Typical Details: Interaction between adjacent scopes

This set is also included with drawing packages given to the install team.

03_PE_Releases

Dedicated to completed work ready for production. Release contents and naming must also satisfy the FE to PE Release checklist.

  • Subfolders copied from _PROJ.JOB_ScopeDescription template and renamed per job.
  • Inside each release folder:
    • Production_Files/: PE Rhino file, SC list, Master Parts List, Lay-Up Summary, optional SHOP model
    • Production_Drawings/: Completed shop drawings by FE and SKs by PE

00_MT_WC_IP_MfgParts

Manufacturing part folders for WC, MT, and IP jobs.

MFG parts naming convention:

  • The enclosing folder is named using the Epicor job number with three trailing digits — e.g., 1130.M.005
  • The Rhino file within is named using the Epicor part number with five trailing digits — e.g., 1130.MT.00022_PE.3dm

03_OUTGOING_Submittals

Three-folder submittal review workflow. See Submittal Review Cycle.

Each job has its own subfolder (PROJ.JOB_ScopeDescription/) containing:

00_Internal_Review

  • Completed shop drawings placed here for QA before submission.

01_Outgoing

  • Reviewed and updated drawings sent to the client for approval. The PM exports a clean (comment-free) PDF copy here after PA approval.

02_Returned

  • Drawings returned by the architect with markups, to be reviewed and picked up by FE.