Folder Structure & File Management Outline
Related Documents: FE Workflow PE Workflow FE to PE Release
Project Organization Overview
The CWK Engineering folder structure organizes all project-related files. Consistent folder structure ensures efficient file location and collaboration across the engineering team.
Full Box Hierarchy
Box/
Awarded/
[4-digit ProjectCode]_[ProjectDescription]/
01 Precon/
02 Project Management/
05_Material_Finish_Log/
03 Engineering/
01_INCOMING_Documents/
00_Contract_Drawings_from_Precon/
01_Addendum_Drawings_Post_Contract/
02_Working_Set/
03_Spec_Sheets/
04_Coordination_Documents/
_AdjacentSub_Drawings_Models/
_Processed_Laser_Scans/
02_WORKING_Drawings_Models/
00_Lead_Project_Eng/
_Shared_Display_Modes/
_Shared_GH/
01_FE_Models/
[PROJ.JOB_ScopeDescription]/
00_GS_Master_Models/
02_CoverSheet_CommonPages/
03_PE_Releases/
[PROJ.JOB_ScopeDescription]/
Production_Files/
Production_Drawings/
00_MT_WC_IP_MfgParts/
[PROJ.M.000 or PROJ.W.000]/
03_OUTGOING_Submittals/
[PROJ.JOB_ScopeDescription]/
00_Internal_Review/
01_Outgoing/
02_Returned/
04 Purchasing/
05 Shipping/
Always use Windows Explorer paths (not Box links) when referencing file locations in release forms and team communications.
PROJECT ROOT FOLDER
- Location:
Box/Awarded/ - Contains all active projects
SPECIFIC PROJECT FOLDER
Naming Convention:
[4-digit ProjectCode]_[ProjectDescription]
Example: 1085_Lucas Retail Expansion and Security Pavilion
DEPARTMENTS Folder
Contains folders for all company departments:
- 01 Sales (Precon)
- 02 Project Management
- 03 Engineering
- 04 Purchasing
- 05 Shipping
03 ENGINEERING Folder Structure
01_INCOMING_Documents
Contains all job-related documents received to date:
00_Contract_Drawings_from_Precon
- Architectural drawing set from the client used for contract/bidding.
- Copies become the working set.
01_Addendum_Drawings_Post_Contract
- Updated architect drawings reflecting changes to existing jobs.
02_Working_Set
- Organized contract drawings used by engineers for modeling and drafting.
03_Spec_Sheets
- Detailed drawings (cut sheets) of devices/components for accurate modeling and submittals.
04_Coordination_Documents
- Documentation for installation coordination:
_AdjacentSub_Drawings_Models/: Floor plans, 3D models from adjacent trades._Processed_Laser_Scans/: Cleaned 3D laser scan files.
02_WORKING_Drawings_Models
Houses working drawings and models:
00_Lead_Project_Eng
_Shared_Display_Modes/: Project-specific display modes for consistent submittal appearance._Shared_GH/: Shared Grasshopper scripts.
01_FE_Models
- Individual job folders copied from
_PROJ.JOB_ScopeDescriptiontemplate and renamed to your job. - FE working file naming:
[PROJ.JOB]_FE_[Description].3dm— e.g.,1094.002_FE_CashWrap.3dm - PE release file naming:
[PROJ.JOB]_PE_YYYYMMDD.3dm— e.g.,1105.007_PE_20250124.3dm 00_GS_Master_Models/: Grouped submittals master models.
02_CoverSheet_CommonPages
Project-level documents that attach to any full project submittal or record set:
- Cover Sheet: Full project job index
- General Requirements: Finish/material tags generated via the Engineering Toolkit from the TRA log
- Master Floorplan / Keyplan: Per level, showing all awarded scope
- Partition Plans: Field dimensions, ceiling heights, blocking, electrical, load calcs if needed
- Pre-Submittal Sets: Scope/design intent clarification
- Typical Details: Interaction between adjacent scopes
This set is also included with drawing packages given to the install team.
03_PE_Releases
Dedicated to completed work ready for production. Release contents and naming must also satisfy the FE to PE Release checklist.
- Subfolders copied from
_PROJ.JOB_ScopeDescriptiontemplate and renamed per job. - Inside each release folder:
- Production_Files/: PE Rhino file, SC list, Master Parts List, Lay-Up Summary, optional SHOP model
- Production_Drawings/: Completed shop drawings by FE and SKs by PE
00_MT_WC_IP_MfgParts
Manufacturing part folders for WC, MT, and IP jobs.
MFG parts naming convention:
- The enclosing folder is named using the Epicor job number with three trailing digits — e.g.,
1130.M.005 - The Rhino file within is named using the Epicor part number with five trailing digits — e.g.,
1130.MT.00022_PE.3dm
03_OUTGOING_Submittals
Three-folder submittal review workflow. See Submittal Review Cycle.
Each job has its own subfolder (PROJ.JOB_ScopeDescription/) containing:
00_Internal_Review
- Completed shop drawings placed here for QA before submission.
01_Outgoing
- Reviewed and updated drawings sent to the client for approval. The PM exports a clean (comment-free) PDF copy here after PA approval.
02_Returned
- Drawings returned by the architect with markups, to be reviewed and picked up by FE.